Ity Mine

    Overview

    Ownership

    • 85% EDV, 10% government of Côte d’Ivoire, 5% SODEMI

    Location

    • Approximately 480 km northwest of Abidjan in southern Côte d'Ivoire

    Mine Attributes

    • Mining Method: Open pit
    • Processing: 4Mtpa CIL (Volumetric upgrades to 5Mtpa in Q4 2019)
    • Gold Recovery: 86% (Optimization Study LOM estimate)

    2020 Key Catalysts

    • Q1 2020 Maiden reserve for the Le Plaque discovery
    • Q2 2020 Updated technical report including new reserves

    Operating Performance

    Operational Data FY-2015 FY-2016 FY-2017 FY-2018 FY-2019
    Mining
    Waste (kt) 311 4,916 5,237 2,901 8,320
    Ore Mined -open pit (kt) 64 1,186 1,410 1,127 5,733
    Processing
    Ore Processed (kt) 71 1,173 1,194 1,307 3,693
    Grade (g/t) 2.39 2.20 1.85 2.49 1.88
    Recovery (%) 81% 93% 83% 81% 86%
    Production (oz) 5,689 75,867 59,026 84,832 190
    Cash Costs
    Cash cost per gold ounce sold (US$/oz) 550 606 733 646 ~542*
    All-in Sustaining Costs (US$/oz) 683 756 906 719 ~616*

    *Preliminary, as FY-2019 results will be published on March 9, 2020.


    Technical Reports

    Download year list
    Date Download Description

    Reserves and Resources

    ITY MINE RESERVES AND RESOURCES

    On a 100% basis. Resources shown inclusive of Reserves. Tonnage
    (Mt)
    Grade
    (Au g/t)
    Content
    (Au koz)
    Proven Reserves0.01.45 2
    Probable Reserves 60.71.55 3,036
    P&P Reserves60.8
    1.55 3,039
    Measured Resource (incl of reserves) 1.4 0.97 44
    Indicated Resources (incl of reserves) 72.2 1.55 3,602
    M&I Resources (incl of reserves) 73.6 1.54 3,646
    Inferred Resources 19.1 1.34 823

     

    Timeline

    Maps

    Ity Birimian Corridor

    Ity CIL Deposits to be added in the study

    Ity high-grade Bakatouo discovery


    Ity Mine Drilling Targets

    Latest News